Optimization of Project Acceleration Using Least Cost Scheduling Method: A Case Study
DOI: https://doi.org/10.26618/bet8bh77
Construction project management, least cost scheduling, project acceleration, critical path method, cost optimization
Abstract
The rapid growth of the construction industry demands effective project management strategies to minimize delays and optimize costs. This study analyzes project acceleration using the Least Cost Scheduling (LCS) method in the construction of State Civil Apparatus (ASN) Ministry of Public Works and Housing (PUPR) flats for National Sports Week (PON) support. The research applies Microsoft Project to determine the critical path and evaluates different acceleration scenarios by increasing working hours by 1, 2, 3, and 4 hours per day. The findings indicate that with a 4-hour work extension, the project duration can be reduced from 390 days to 325 days, achieving a time saving of 65-days. However, this acceleration increases total project costs from IDR 20,436,612,368.92 to IDR 30,830,058,031.32, representing a 50.86% cost increase. The most cost-efficient balance was achieved by extending the workday by three hours, reducing project duration to 351 days with a 45.20% cost increase. These results provide valuable insights for construction project managers in selecting efficient acceleration strategies while considering financial feasibility.
References
H. A. Rani, F. F. Maina, M. S. Aqsha, and M. H. Mubarak, “Time and cost efficiency analysis of Aceh Tengah Regency POM Workshop Project: A Critical Path Method approach,” International Journal of Engineering Science Technologies, vol. 8, no. 3, pp. 34–46, 2024. https://doi.org/10.29121/ijoest.v8.i3.2024.604
S. Javed, M. I. Hussain, A. M. Al Aamri, and J. Akhtar, “Investigation on factors causing construction delay and their effects on the development of Oman’s construction industry,” EUREKA: Physics and Engineering, vol. 6, pp. 33-44, 2022. https://doi.org/10.21303/2461-4262.2022.001865
A. F. Elkliny, H. M. Sanad, and E. E. Etman, “Time-cost-quality tradeoff considering resource-scheduling problems,” Ain Shams Engineering Journal, vol. 14, no. 11, 102524, 2023. https://doi.org/10.1016/j.asej.2023.102524
K. Abuhasel, “Sustainable green city development project analysis using the Critical Path Method (CPM) and the crashing project method on time and cost optimization,” Engineering, Technology and Applied Science Research, vol. 13, issue 3, pp. 10973-10977, 2023. https://doi.org/10.48084/etasr.5980
C. Hendrickson and T. Au, “Project management for construction: Fundamental concepts for owners, engineers, architects, and builders,” Prentice Hall, 2022. 978-0137312665.
F. Afrian, D. Kurnia, and E. Supriyadi, “Optimalisasi pelaksanaan proyek porta cabin 40 feet dengan metode Critical Path Method (CPM) di PT Tepat Guna Teknologi Nusantara,” Teknologi: Jurnal Ilmiah dan Teknologi, vol. 4, no. 1, pp. 11-18, 2021. https://doi.org/10.32493/tkg.v4i1.21847
W. Y. Rio, S. W. Astuti, and D. M. R. Kartika, “Penjadwalan ulang menggunakan Critical Path Method pada pembangunan rumah tinggal Cluster Pineville Grand City Balikpapan,” INNOVATIVE: Journal of Social Science Research, vol. 4, no. 1, pp. 5691-5701, 2024. https://j-innovative.org/index.php/Innovative/article/view/7142
X. Papuraj, N. Izadyar, and Z. Vrcelj, “Cost optimization in Building Construction Projects with Special Reference to Kathmandu Valley of Nepal,” American Journal of Science, Engineering and Technology, vol. 6, issue 1, pp. 8-19, 2021. https://doi.org/10.11648/j.ajset.20210601.12
N. Essam, L. Khodeir, and F. Fathy, “Approaches for BIM-based multi-objective optimization in construction scheduling,” Ain Shams Engineering Journal, vol. 14, no. 6, 102114, 2023. https://doi.org/10.1016/j.asej.2023.102114
H. Andraiko, P. Dwiyanto, and W. Citra, “Integrasi metode lean construction dan BIM 4D pada proyek renovasi gedung Pemerintah Lhokseumawe Aceh untuk meningkatkan kinerja waktu,” Jurnal Teknik Sipil, vol. 12, no. 1, pp. 1-8, 2023. https://jurnal.usk.ac.id/JTS/article/view/27538
M. A. Al-Sinan, A. A. Bubshait, and Z. Aljaroudi, “Generation of construction scheduling through machine learning and BIM: A blueprint,” Buildings, vol. 14, no. 4, 934, 2024. https://doi.org/10.3390/buildings14040934
K. E. Pratiwi, F. N. Abdi, and E. Budiman, “Optimalisasi biaya dan waktu pelaksanaan proyek dengan metode least cost analysis,” Teknologi Sipil: Jurnal Ilmu Pengetahuan dan Teknologi, vol. 4, no. 2, pp. 20-29, 2020. https://ocs.unmul.ac.id/index.php/TS/article/view/5235
S. Aminbakhsh and A. M. Abdulsattar, “Optimizing three-dimensional trade-off problem of time–cost–quality over multi-mode projects with generalized logic,” Buildings, vol. 14, no. 6, 1676, 2024. https://doi.org/10.3390/buildings14061676
X. Zou and L. Zhang, “A constraint programming approach for scheduling repetitive projects with atypical activities considering soft logic,” Automation in Construction, vol. 109, 102990, 2020. https://doi.org/10.1016/j.autcon.2019.102990
G. R. Rakasyiwi, B. Witjaksana, and H. T. Tjendani, “Project scheduling analysis using the Critical Path Method – Case study: Subsidized house construction project in Hill Mulya Housing, Samarinda City,” International Journal on Advanced Technology, Engineering, and Information System, vol. 1, no. 4, pp. 73–80, 2022. https://doi.org/10.55047/ijateis.v1i4.480
H. A. Rani, A. R. Radzi, A. R. Alias, S. Almutairi, and R. A. Rahman, “Factors affecting workplace well-being: Building construction projects,” Buildings, vol. 12, no. 7, 910, 2022. https://doi.org/10.3390/buildings12070910
R. A. Permana, M. Fauzan, S, Malaysi, T. M. Hafli, D. Sarana, and M. Mukhlis, “Comparative study of the fast track method with the crash program method in accelerating time and costs,” PRINCE: Journal of Planning and Research in Civil Engineering, vol. 3, no. 2, pp. 426-432, 2024. https://ejournal.unida-aceh.ac.id/index.php/prince/article/view/800
H. A. Rani, J. Amin, A. Ayob, and D. Al Rahmatillah, ”Risk probability of time and cost on building construction project: A monte carlo simulation,” Journal of Innovation and Technology, vol. 3, no. 2, pp. 60-68, 2022. https://ojs.umrah.ac.id/index.php/jit/article/view/5192
J. C. Chen, T. L. Chen, Y. Y. Chen, and M. Y. Chung, “Multi-resource constrained scheduling considering process plan flexibility and lot streaming for the CNC machining industry,” Flexible Services and Manufacturing Journal, vol. 36, no. 3, pp. 946–993, 2024. https://doi.org/10.1007/s10696-023-09514-w
S. Lu, C. Li, R. Wang, and Y. Huo, “Research on the day-ahead scheduling optimization method of medium-depth geothermal cascade heating system,” Journal of Building Engineering, vol. 82, 108184, 2024. https://doi.org/10.1016/j.jobe.2023.108184
C. Hu, J. Wang, and Y. Mei, “Uncertain time-resource-cost trade-off models for construction project schedule,” KSCE Journal of Civil Engineering, vol. 25, no. 8, pp. 2771-2778, 2021. https://doi.org/10.1007/s12205-021-1798-7
S. Aminbakhsh, R. Sönmez, and T. Atan, “ε-constraint procedures for Pareto front optimization of large size discrete time/cost trade-off problem,” European Journal of Operational Research, vol. 322, no. 3, pp. 753-769, 2025. https://doi.org/10.1016/j.ejor.2024.11.032
Published
Issue
Section
License
Copyright (c) 2025 Jurnal Linears

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.